Activity Base Week

ResiDex will allow you to create up to four Base weeks per activity schedule group.  Creating base weeks will allow you to create a week of activities that may rotate.  It will streamline your data entry if the activity times remain the same but the activity itself varies.  

Create a Base Week

  • On the Act. Setup screen, choose the Schedule Group
  • Click on Base Week 1, 2, 3 or 4
  • Click on "new" and enter the Base Week activities in the grid below the weekly view