Activity Base Week
ResiDex will allow you to create up to four Base weeks per activity schedule group. Creating base weeks will allow you to create a week of activities that may rotate. It will streamline your data entry if the activity times remain the same but the activity itself varies.
Create a Base Week
- On the Act. Setup screen, choose the Schedule Group
- Click on Base Week 1, 2, 3 or 4
- Click on "new" and enter the Base Week activities in the grid below the weekly view